Summary/Background:
The design of the Taxiway A reconstruction will be $266,318 paid with the FAA grant $239,686 (90%); NMDOT-Aviation - $13,316 (5%) and Town of Taos Match - $13,316 (5%). The NMDOT-Aviation grant was approved at the 7/23/19 meeting and has been sent back to the State for final execution.
Summary/Background: Approval to utilize the State Purchasing policy in place of the Town Budget Policy for the following:
Installation of sidewalk along walking path, installation of drive pad for entrance and along the stage, stand up curb for the grass and gravel pave materials that were installed by Town staff and standup curb along the ditch on the east side of the stage. This work is to help prevent damaging of the grass and to connect the walking paths in front of the stage for regular constituents that frequent the park.
Summary/Background: Approve the contract TT-20-50 in the amount of $55,162.94 exclusive of GRT to A & S Construction to install the walking path in Kit Carson Park with the approval to utilize State Purchasing policy in place of the Town Budget Policy.